Close WindowPrint
TSP: 
TSP Name: 
Critical Notice Description: 
Notice Effective Date: 
Notice Effective Time: 
Notice End Date: 
Notice End Time: 
Notice Identifier: 
Notice Status Description: 
Notice Type: 
Posting Date: 
Posting Time: 
Prior Notice Identifier: 
Required Response
  Indicator Description: 
Response Date: 
Response Time: 
Subject: 
007932908
Texas Eastern Transmission, LP
Critical notice
06/11/2021
09:00:00 AM
06/12/2021
09:00:00 AM
109228
Initiate
Capacity Constraint
06/10/2021
03:46:34 PM


No response required


TE Pipeline Conditions for 6/11/2021


Notice Text:

For Gas Day June 11, 2021, Texas Eastern (TE) has approved and scheduled nominations at each pipeline segment and meter station up to TE's operational capacity. The following locations have been restricted due to requested nominations exceeding TE's operational capacity:

TE has restricted interruptible and a portion of secondary out of path nominations that exceed entitlements sourced on the Leidy Line for delivery off the Leidy Line. No increases in receipt nominations will be accepted on the Leidy Line

TE has restricted interruptible and secondary out of path nominations that exceed entitlements sourced from points east of Lambertville for delivery to points west of Lambertville. No increases for receipt nominations sourced from points east of Lambertville for delivery to points west of Lambertville will be accepted.

TE has restricted interruptible and secondary out of path nominations that exceed entitlements delivering to locations between Marietta and Lambertville on TE's 36-inch line which have receipts sourced outside this delivery area. No increases in nominations delivering to locations between Marietta and Lambertville on TE's 36-inch line which have receipts sourced outside this delivery area will be accepted.

TE has restricted interruptible, secondary out of path, secondary in path nominations not to a primary delivery point, and a portion of secondary in path nominations to a primary delivery point flowing through the Uniontown Compressor Station. TE will not allow any increases in receipts sourced from points west of Uniontown for delivery to points east of Uniontown except for Firm No-Notice services.

TE has restricted a portion of interruptible nominations sourced upstream of the Marietta Mainline Extension for delivery on the Marietta Mainline Extension. No increases in deliveries sourced upstream of the Marietta Mainline Extension for delivery downstream of the Marietta Mainline Extension will be accepted.

TE has restricted interruptible, secondary out of path, and secondary in path nominations sourced either on the M1-24", M2-24", M2-30" north of Berne Compressor Station (Berne) or in M3 for delivery south of Berne. No increases for receipt nominations sourced either in the M1-24", M2-24", M2-30" north of Berne or in M3 for delivery south of Berne will be accepted.

TE has restricted interruptible, secondary out of path, secondary in path, and a portion of primary firm nominations sourced either in the M1-24", M2-24", M2-30" north of Danville Compressor Station (Danville) or in M3 for delivery south of Danville. No increases for receipt nominations sourced either in the M1-24", M2-24", M2-30" north of Danville or in M3 for delivery south of Danville will be accepted.

TE has restricted interruptible, secondary out of path, and secondary in path nominations sourced either on the M1-24", M2-24", M2-30" north of Tompkinsville Compressor Station (Tompkinsville) or in M3 for delivery south of Tompkinsville. No increases for receipt nominations sourced either in the M1-24", M2-24", M2-30" north of Tompkinsville or in M3 for delivery south of Tompkinsville will be accepted.

TE has restricted interruptible, secondary out of path, and secondary in path nominations sourced either in the M1-24", M2-24", M1-30" north of Barton Compressor Station (Barton), M2-30" or in M3 for delivery south of Barton. No increases for receipt nominations sourced either in the M1-24", M2-24", M1-30" north of Barton, M2-30" or in M3 for delivery south of Barton will be accepted.

TE has restricted interruptible and a portion of secondary out of path nominations that exceed entitlements sourced in STX, WLA, ELA, M1-30", M2-30", M3 and receipt points north of Sarahsville on the M2-24 for delivery south of Sarahsville to the M1-24", M2-24" or delivery locations in ETX between Longview and N. Little Rock. No increases in receipts sourced in STX, WLA, ELA, M1- 30", M2-30", M3 and receipt points north of Sarahsville on the M2-24 for delivery to the M1-24", M2-24" or delivery locations in ETX between LGV and N. Little Rock will be accepted.

TE has restricted interruptible and a portion of secondary out of path nominations that exceed entitlements sourced in in STX, WLA, ELA, M1-30", M2-30", M3 and receipt points north of Lebanon on the M2-24 for delivery south of Lebanon to the M1-24", M2-24" or delivery locations in ETX between Longview and N. Little Rock. No increases in receipts sourced in STX, WLA, ELA, M1- 30", M2-30", M3 and receipt points north of Lebanon on the M2-24 for delivery to the M1-24", M2-24" or delivery locations in ETX between LGV and N. Little Rock will be accepted.

TE has restricted interruptible and a portion of secondary out of path nominations that exceed entitlements sourced either in ETX or STX north of Speaks Compressor Station (including the Wilcox system) for delivery to M3, M1-30, M2-30, ELA, WLA, and to STX east of Speak and STX south of Speaks (McAllen line). No increases in receipts sourced in ETX, STX north of Speaks Compressor Station (including the Wilcox system) Will be accepted.

TE has restricted a portion of interruptible nominations sourced either in WLA north of Gillis Compressor Station (Gillis), ELA, M1-24", M2-24", M1-30", M2-30" or in M3 for delivery south of Gillis in WLA, STX, ETX (south of Longview). No increases for receipt nominations sourced either in WLA north of Gillis, ELA, M1-24", M2-24", M1-30", M2-30" or in M3 for delivery south of Gillis in WLA, STX and ETX (south of Longview) will be accepted.

TE has scheduled and sealed nominations sourced in ETX for delivery in STX, WLA, or ELA. No increases in receipt nominations sourced in ETX for delivery in STX, WLA or ELA will be accepted.

TE has restricted and sealed nominations on TE's lease capacity with Algonquin Gas Transmission (AGT) to TE's Maximum Daily Quantity (MDQ).

TE has scheduled and sealed nominations sourced at receipt meters associated with the NEXUS/TE leased capacity in accordance with TE's Maximum Daily Receipt Obligations (MDRO).

TE has restricted interruptible, secondary out of path, and a portion of secondary within path delivery nominations to meter 75919 (TRANSCO - BELLE MEADE, NJ). No increases in delivery nominations to meter 75919 will be accepted.

TE scheduled and sealed nominations to meter 75037 (DTI - WAYNESBURG, PA(D 70037/R 76037). No increases in delivery nominations to meter 75037 will be accepted.

TE has Force Balanced a portion of short TABS pools in Access Area zones ETX, STX, ELA and WLA and Market Area zones M1-24, M2-24, M1- 30, M2-30 and M3 will continue to throughout subsequent nomination cycles.

TE has Force Balanced a portion of long TABS pools in Access Area zones ETX, STX and Market Area zones M1-24 and M2-24 and will continue to throughout subsequent nomination cycles.

TE requires all shippers and point operators in Market Area Zones M1-24 and M2-24 to keep actual daily takes out of the system equal to or less than scheduled quantities regardless of their cumulative imbalance position unless otherwise coordinated with your operations account representative. All receipt point operators in Market Area Zones M1-24 and M2-24 are required to keep actual daily receipts into the system equal to or greater than scheduled quantities regardless of their cumulative imbalance position unless otherwise coordinated with your operations account representative.

TE requires all shippers and point operators in Access Area Zones STX, ETX, WLA and ELA and Market Area Zones M1-30 and M3 to carefully review demand for gas and schedule gas consistent with daily needs and to tender and receive gas consistent with confirmed nominations regardless of their cumulative imbalance position unless otherwise coordinated with your operations account representative.

Additionally, the Market Area Zone M2-30 OFO issued May 29, 2021 will remain in effect until further notice.

Furthermore, TE requires all Power Plant Operators in the Market Area Zones M1-24 and M2-24 to provide information mandated by FERC Order No. 698. Information required includes the hourly consumption profile of directly connected power generation facilities.

Please contact your Operations Account Representative should you have any questions.